Construction of City Center West Orange's Phase 1 continues with building AB's foundation, the installation of ConSpan Arches for the Lake Bennet promenade, and the flattening and addition of curbs to the Blackwood Extension. Our construction team has been busy working despite several summer rain storms.
Monday, June 22nd
- No VSC or drilling, both machines are down
- Continuing work on building AB's foundation
- Installing rebar container
- Continuing digging dirt around the lake for Conspan Arch placement
- Continuing Blackwood curb installments
- Load Test on building CJ will be conducted at 7:30 tomorrow morning