Construction work continues despite the beginning of Hurricane Season.

June 1st

  • Constructing a block wall and elevation on the island
  • Continuing installing rebar on AB Building
  • Continuing the stone columns on AB Building
  • Constructing next rebar location placement
  • Ocoee Utilities is out inspecting the storm drainage on Blackwood extension

June 2nd

  • Continuing construction on block wall and elevation on the island
  • Continuing installation of rebar on AB Building
  • Continuing the stone columns on AB Building
  • Constructing next rebar location placement

June 3rd

  • Vibro drill is down because of a fluid leak, no stone columns today
  • Continuing the installation of rebar for AB Building
  • Constructing next rebar location placement
  • Continuing construction of block wall and elevation on the island

June 4th

  • Storms slowing down progress
  • Continuing construction of block wall and elevation on the island
  • Vibro drill down due to weather conditions, stone columns resume when the weather clears up

June 5th

  • Continuing construction of block wall and elevation on the island
  • Continuing installation of rebar on AB Building
  • Continuing the stone columns for AB Building
  • Finishing AB Building stone columns (marks all 760 Vibro Stone Columns)