Construction work continues despite the beginning of Hurricane Season.
June 1st
- Constructing a block wall and elevation on the island
- Continuing installing rebar on AB Building
- Continuing the stone columns on AB Building
- Constructing next rebar location placement
- Ocoee Utilities is out inspecting the storm drainage on Blackwood extension
June 2nd
- Continuing construction on block wall and elevation on the island
- Continuing installation of rebar on AB Building
- Continuing the stone columns on AB Building
- Constructing next rebar location placement
June 3rd
- Vibro drill is down because of a fluid leak, no stone columns today
- Continuing the installation of rebar for AB Building
- Constructing next rebar location placement
- Continuing construction of block wall and elevation on the island
June 4th
- Storms slowing down progress
- Continuing construction of block wall and elevation on the island
- Vibro drill down due to weather conditions, stone columns resume when the weather clears up
June 5th
- Continuing construction of block wall and elevation on the island
- Continuing installation of rebar on AB Building
- Continuing the stone columns for AB Building
- Finishing AB Building stone columns (marks all 760 Vibro Stone Columns)