VIRGINIA INTERNATIONAL GATEWAY UPDATE
In June 2018, The Port of Virginia accepted the final load of 26 new rail-mounted gantry (RMG) cranes at VIG, where $320 million is being invested to expand operations. These cranes will support operations in 13 new container stacks. As of November 1, 2018, there will be 10 new stacks placed into operation. The first newly-configured rail bundle is now operating, served by two semi-automated cantilever rail-mounted gantries (CRMGs). VIG’s inbound truck interchange offers four newly-constructed lanes. An 800-foot expansion of VIG’s wharf will be completed by late November. This project will expand VIG’s annual throughput capacity from 650,000 units to 1.2 million container units; a 550,000 unit capacity increase.
VIG PROJECT UPDATE TIMELINE
- May 2018 - VIG, NIT, RMT, PMT all on single operating system, N-4
- June 2018 - First portion of expanded rail tracks placed in service. PRO-PASS truck reservation system live at VIG 0100-1000
- September 2018 - 4 new inbound gate lanes open
- November 2018 - 11 of 13 new container stacks online. Wharf extension complete
- January 2019 - All 13 new container stacks in service. Delivery of 4 new STS cranes
- March 2019 - New STS cranes in service
- June 2019 - Rail expansion complete. VIG Phase II Expansion complete
NORFOLK INTERNATIONAL TERMINALS UPDATE
In January 2018, construction on the historic $375 million NIT expansion got underway, with project completion expected by mid-year 2020. The centerpiece of the expansion is the construction of 30 semi-automated container stacks at NIT South, served by 60 newly-constructed rail-mounted gantry (RMG) cranes. By January 1, 2019, 12 of NIT’s new RMG stacks will be in service. This project will expand NIT’s annual throughput capacity by 400,000 container units, going from 850,000 to 1.25 million container units; a 46% percent increase.
NIT PROJECT TIMELINE
- January 2018 - Container stack construction begun
- March 2018 - Upgraded PRO-PASS truck reservation system live at NIT 0500-1100
- October 2018 - First three container stacks with new RMG cranes placed in service (beginning of Phase I)
- November 2018 – Three additional containers stacks with new RMG cranes placed in service (6 of 30)
- December 2018 – PHASE II construction begins. Six RMGs delivered (24 of 60). Three additional container stacks with new RMG cranes placed in service (9 of 30)
- February 2019 - 12 new RMG container stacks in service (12 of 30 stacks complete). PHASE I complete.
- PHASE II July 2019-October 2019 - Six new container stacks placed in service (18 of 30 stacks complete)
- PHASE III May 2019 - Construction begins
- PHASE III February 2020-June 2020 - 12 new container stacks placed in service (All 30 stacks online)