One Step Closer to the Lake Road.

We're more than halfway through the month of July, and we continue to make progress on the Conspan Arches for the lake road, the foundation for Building AB is almost complete, and stone columns are being placed for Building CJ's foundation. To top it off, we are scheduled to complete this phase of construction in October!

July 6th - Monday

  • Vibro Stone Columns continuing for Building CJ
  • Continuing work on Building AB's foundation
  • Installing rebar sheets
  • Moved crane into place for next conspan movement

July 7th - Tuesday

  • Vibro Stone Columns continuing on Building CJ
  • Pouring more concrete for the foundation of Building AB
  • Finished Sub-base on Blackwood Road Extension
  • Start laying asphalt for the Blackwood Extension on Monday

July 8th - Wednesday

  • Vibro Stone Column maintenance day
  • Conspan Arches #1 - #5 installed around Lake Bennet Island

July 9th - Thursday

  • Welding on new pieces to the Vibro Stone Column machine
  • Filling dirt and setting stone between Conspan Arches forming the foundation of the lake road

July 10th - Friday

  • Vibro Stone Columns continuing for Building CJ's foundation prep
  • Preparing dirt levels for installing Conspan Arches
  • Filling dirt and setting stone between Conspan Arches

July 13th - Monday

  • Vibro Stone Columns continue being dug for the foundation of Building CJ
  • Filling dirt and setting stone between Conspan Arches forming foundation of future road
  • Begin paving the Blackwood Road Extension, first asphalt layer
  • Installing rebar for Building AB's foundation
  • Digging last few holes for rebar locations

July 14th - Tuesday

  • Filling dirt and setting stone between Conspan Arches for the foundation of the lake road
  • VSC mechanic day
  • Installing rebar for Building AB's foundation
  • Assembling Building CJ's rebar

July 15th - Wednesday

  • VSC mechanic day
  • Installing the last parts of rebar for Building AB's foundation
  • Assembling Building CJ's rebar
  • Moving dirt for the Conspan Arches on the South end

July 16th - Thursday

  • Installing the last sections of rebar for Building AB's foundation
  • Assembling Building CJ's rebar
  • Beginning to dig the North side of the Conspan Arches
  • Installing brick wall on the South end of the Conspan Arches

July 17th - Friday

  • Pre-drill broke just after lunch
  • Building CJ had some holes drilled with the Vibro Stone Column machine
  • Continuing to install the brick wall on the South end of the Conspan Arches