We're more than halfway through the month of July, and we continue to make progress on the Conspan Arches for the lake road, the foundation for Building AB is almost complete, and stone columns are being placed for Building CJ's foundation. To top it off, we are scheduled to complete this phase of construction in October!
July 13th - Monday
- Vibro Stone Columns continue being dug for the foundation of Building CJ
- Filling dirt and setting stone between Conspan Arches forming foundation of future road
- Begin paving the Blackwood Road Extension, first asphalt layer
- Installing rebar for Building AB's foundation
- Digging last few holes for rebar locations