The past two weeks continued the work being done on Blackwood's Extension and Lake Bennet road with the Conspan Arches. Also, significant progress was made on Building CJ's stone columns and rebar assembly.
July 21st - Tuesday
- Digging and flattening dirt north of Conspan Arches
- Continue building up the wall and filling with dirt between Conspan Arches
- Concrete pouring for Building AB at 5:00am
- Construction Meeting: begin digging Building CJ's rebar on light walls (next Tuesday) and possibly concrete next Thursday