CSAH 12 (Stillwater Road/75th Street) Safety & Management Project April 26, 2019 Construction Update

Project Schedule

LOCAL BUSINESSES REMAIN OPEN - VETERANS PARK AVAILABLE FOR PARKING

This Week

  • Xcel Energy advanced work on their 12" gas line.

Next Week

  • Early next week, crews will be working on County Highway 12 east of Mahtomedi Ave/Wildwood Road. This work will close the roadway to traffic.
  • County Highway 12 from Highway 244 to Mahtomedi Avenue/Wildwood Road will be opened.
Please follow the posted detour route.

Upcoming Work

  • Crews will continue working east, requiring a full closure of County Highway 12, between Mahtomedi Ave/Wildwood Road and Forest Ave. Traffic will be detoured via Highway 36/694.

Construction Contact: Jennifer Solseth (651-529-2939)

A camera was placed on-site and takes a picture every 12-14 minutes during the entire construction project. This is a great way to view recent activity and the progress throughout construction.