What is happening?
- A new 12,180 SF addition to the existing building. This includes a new precast gym, bathrooms, storage areas, conference rooms, corridors, learning commons, receiving area, and a new freezer/cooler. We will also be performing sitework improvements to the parking lot during the Spring/Summer phase.
Schedule
- Start Date - 12/22/2020
- Estimated Construction Completion Date - 8/23/2021
Weekly Updates
Work in Progress
- Cooler/freezer is installed, and shelving going in next Monday (pictured).
- Loading dock and back turnaround parking lot in progress.
- Exterior landscaping in progress
- Learning commons space
- Bathrooms in Area B near gym addition
- Existing cafeteria drywalling and taping, painting, and installing ceiling grid
Drone Video
Milestone dates
Kraus-Anderson
Jason Peterson, Senior Project Manager | jason.peterson@krausanderson.com
Andy Thompson, Project Manager | andy.thompson@krausanderson.com
Terry Coleman, Project Superintendent | terry.coleman@krausanderson.com
Wold Architects
Kyle Hoverson, Designer | khoverson@woldae.com