Bond repairs Aldine Independent school district

To Complete by 2020

On November 3, 2015 community voters approved a $798 million-dollar bond proposal for the construction of new schools, renovations, enhancements, and repairs to meet the growth needs of the school district over the next five years.

The Bond Repairs Program is addressing 60 Aldine ISD facilities with repairs and upgrades at every classification including Pre-Kindergarten, Elementary, Middle, and High Schools. The Bond Repairs has addressed facility upgrades which increase the life cycle and the visual appeal of the building.

Nimitz Sr. High School

May 2019 Updates

At Nimitz Senior High School, the first set of restrooms renovations is 85% complete and the mechanical equipment installation is 35% complete

Teague Middle School

May 2019 Updates

The first set of restrooms is 65% complete, the roof repairs are 35% complete and the mechanical equipment installation is 65% complete.

Odom Elementary School

May 2019 Updates

At Odom Elementary School, the roof replacement is 90% complete, the installation of the new LED light fixtures is 35% complete and the mechanical insulation is 70% complete.

Thompson Elementary

May 2019 Updates

The first set of student restrooms has been completed and turned over to the school. The demolition of the second set of student restrooms has begun with the removal of underground plumbing and the installation of new underground plumbing is underway.

Eisenhower Sr. High School

May 2019 Updates

The installation of floor and wall tile is complete, and the installation of toilet partitions are underway in both boys and girls restrooms. The removal and replacement of new air handling units are underway in the gym area.

Carver Sr. High School

May 2019 Updates

The installation of floor and wall tile is complete, and the installation of toilet partitions are underway in both boys and girls restrooms. The removal and replacement of new air handling units are underway in the gym area.

Aldine Sr. High School

The electricians continue transferring wiring from the old conduits into the new conduits as they continue along the roof. The roof tear-off and replacement is underway and 25% complete.

The installation of the chill water piping and the installation of the new conduits and stands continue and is 85% complete.

Aldine Senior High School

April 2019 Updates

The installation of chill water piping and the installation of the new conduits and stands are 80% complete. The electricians are currently transferring wiring from old conduits into the new conduits. The roof tear-off and replacement is 15% complete.

At Aldine Senior High School, the control wiring and control box installations continue and are currently at 80% complete. The replacement of valves on existing rooftop units and fan coil units is underway

Carver High School Repairs

April 2019 Updates

The Carver High School Repairs project are on-going. The roof repairs in the pool and technology area are complete. The installation of floor tile is being installed in both boys and girl’s restrooms.

Eisenhower Sr. High School

April 2019 Updates

he first set of restrooms is complete with the installation of tile, toilet partitions, and accessories. The second set of restroom demolition started this month.

The roof repairs have begun and are scheduled to be complete by the Summer of 2019. The mechanical repairs continue with the replacement of rooftop units and control wiring.

Thompson Elementary

April 2019 Updates

The installation of LED lighting fixtures and plumbing fixtures in the first set of restrooms is complete. After the completion and turnover of the first set of student restrooms, the demolition of the second set of student restrooms started. The project is 30% complete and is scheduled to be complete by the Summer 2019.

Nimitz Sr. High school

April 2019 Updates

The installation of new LED light fixtures is complete. The first set of restrooms renovations is 60% complete and the mechanical equipment installation is 30% complete.

Teague Middle School

April 2019 Updates

The installation of new LED light fixtures and the replacement of the ceiling tile and grid is complete. The first set of restrooms is 60% complete and the mechanical equipment installation is 40% complete.

Odom Elementary School

April 2019 Updates

The electrical conduit installation is complete. The roof replacement is 80% complete and the installation of new LED light fixtures is 30% complete.

Thompson Elementary

March 2019 Updates
The installation of LED lighting fixtures and plumbing fixtures has been complete in the first set of restrooms.

The toilet partitions are being installed in the first set and the second set of restrooms will begin after the turnover of the first set of restrooms. The project is 40% complete and is scheduled to be complete by the Summer 2019.

Eisenhower High School

March 2019 Updates

Track Replacement & Restroom Repairs

The sod has been laid and the track and parking area has been graded. The rubber structural surface has been applied and striping of the track will follow.

The first set of restrooms is 90% complete with the installation of tile, toilet partitions and accessories.

The mechanical repairs continue with the replacement of roof top units and control wiring to those units are also underway. The project is 30% completed.

Carver High School

March 2019 Updates

The installation of floor tile, sinks and toilets is being performed in both boys and girl’s restrooms. The project is 60% complete and is expected to be complete by the Fall of 2019.

The roof replacement was complete in the pool area and the work on the roof in the technology area continues.

Nimitz High School

March 2019 Updates

Track Replacement & Restrooms Upgrades

The asphalt has cured and the track running surface has been installed. The grading of swales around the perimeter has been cut and the forming of the landing has been repaired. Due to inclement weather the project is set for completion by early Spring of 2019.

The first set of restrooms renovations is 60% complete

Aldine Sr. High School

March 2019 Updates

The installation of chilled water piping and the installation of the new conduits and stands are 80% complete.

Aldine Senior High School, the control wiring and control box installations continues and is currently at 80% complete.

The roof tear-off and replacement continues and will continue throughout the project. The project is 30% complete and is expected to be complete by the Winter of 2020.

The electricians are currently transferring wiring from old conduits into the new conduits and completing the circuits to ensure that everything is functioning correctly.

Thompson Elementary

February 2019 Updates

The plumbing on the first set of restrooms is complete. The floor, wall tile and plumbing fixtures is underway. The project is scheduled to be completed by the Summer of 2019.

Odom Elementary

February 2019 Updates

the electrical conduit installation is complete, the roof replacement is 70% complete, and the installation of new LED light fixtures is 20% complete.

Teague Middle School

February 2019 Updates

Mechanical equipment installation is 20% complete

Nimitz Sr. High School

February 2019 Updates

Track Repairs & Restroom Updates

The irrigation system was installed and back filled. Testing of the irrigation system was completed and is working properly. The removal of the silt fence is underway.

At Nimitz Senior High School, the first set of restrooms is 50% complete, the mechanical equipment installation is 20% complete, and the installation of new LED light fixtures is 90% complete.

Carver High School

February 2019 Updates

The roof replacement is being completed in pool and technology area. The wall and floor tile in the restrooms have been completed and the installation of toilet partitions and plumbing fixtures will follow. The project is 50% complete and is expected to be complete by the Fall of 2019.

Aldine Sr. High School

February 2019 Updates

The installation of chiller water piping and the installation of the new conduits and stands continues.

The roof tear-off and replacement has begun and will continue throughout the project. The project completion is scheduled for late Winter of 2020.
At Aldine Senior High School, the control wiring and control boxes are underway and currently at 75% complete.

Thompson Elementary School

January 2019 Updates

The plumbing is underway with installation of floor drains and new plumbing walls. The project is scheduled to be complete by the Summer of 2019.

Nimitz Sr. High School

January 2019 Updates

Track Repairs

Striping the track surface started

Eisenhower High School

January 2019 Updates

The first set of restrooms has been completed with the installation of tile, toilet partitions and accessories. Demolition of the second set of restrooms will follow. The project is currently 15% complete.

The project completion is scheduled for Fall of 2019.

Carver High School

January 2019 Updates

The installation of wall and floor tile, painting, plumbing partitions has been completed in the second set of restrooms.

The replacement of ceiling tiles in cafeteria and kitchen have also been completed. The roof repairs are in progress on the main building, pool area and the auditorium. The plumbing fixtures and tile are being installed. The project is 40% complete and is expected to be completed by the Fall of 2019.

Aldine Senior High School and MacArthur Senior High School Building Automation System Repairs

January 2019 Updates

MacArthur Senior High School

The controls, control valves, valve actuators and float switches have been completed. Contractors are currently working on the punch list items.

Aldine Senior High School

The control wiring and control boxes are being installed and currently at 85% complete. The overall project is 65% complete and the project completion is scheduled for Winter of 2019.

Aldine Sr. High School

January 2019 Updates

The Aldine Senior High School Repairs Project includes replacements and repair of the mechanical system and a total roof replacement.

In the administration areas of the roof, the installation of chiller water lines has been completed. In preparation for the roof installment, the roof curbs have been raised and the installation of the new electrical conduits is ongoing.

The project completion is scheduled for late Winter of 2020.

Nimitz Track Updates

December 2018 Updates

The project has begun with surface removal, forming of curb, and placement of asphalt has been completed. The track running surface installation will begin once asphalt curing is completed. The project completion is scheduled for Winter of 2019

Thompson Elementary School

December 2018 Updates

The Thompson Elementary School Repairs Project includes new ceiling tile, new plumbing fixtures, new toilet partitions and lighting upgrades.

The project has begun construction and demolition in restrooms has been completed. The plumbing and electrical will follow along with installation of ceiling and wall tile. The project is scheduled to be completed by the Summer of 2019.

Teague Middle School

December 2018 updates

Teague Middle School Repairs Project includes consists of restroom upgrades, replacement of lighting fixtures, painting, ceiling tile and ceiling grid replacements, mechanical and roof repair and replacements.

The demolition of the restrooms at Teague Middle School has begun and is currently at 10% complete. The project completion is scheduled for late Winter of 2020.

Carver High School

December 2018 Updates

The Carver High School Repairs Project includes repairs and replacement of mechanical systems, roof repairs, restroom repairs, auditorium stage lighting upgrades and floor replacements in the cafeteria.

Aldine Sr. High School

December 2018 Updates

The Aldine Senior High School Repairs Project includes replacements and repair of the mechanical system and a total roof replacement.

The control wiring and control boxes are being installed and currently at 75% complete.

Odom Elementary

December 2018 Updates

Odom Elementary School Repairs Project includes consists of restroom upgrades, replacement of lighting fixtures, painting, ceiling tile and ceiling grid replacements, mechanical and roof repair and replacements.

Eisenhower High School

December 2018 Updates

The project has begun with surface removal, forming of curb, and placement of asphalt has been completed. The track running surface installation will begin once asphalt curing is completed.

The project completion is scheduled for Winter of 2019.

ALDINE Sr. HIGH SCHOOL

November 2018 Updates

The Aldine Senior High School Repairs Project includes replacements and repair of the mechanical system and a total roof replacement. The project will begin with phase one of construction the roof replacement in unobstructed areas.

The project is scheduled to begin in mid-Fall of 2018. The project completion is scheduled for late Winter of 2019.

MECHANICAL REPAIR PROJECT

October 2018 Updates

Nimitz 9th Grade, Parker Elementary and Stovall EC/PK/K School

The cleaning of coils and replacements of belts and motors on the air handling units 100% complete. The replacement of fan coil units and air handling units are ongoing. The project completion is scheduled for late Winter of 2018.

Drew Academy

September 2018 Updates

Paneling and LED lighting installation at Drew Academy is at near completion

The new air conditioning units were installed on the roof

New glass store front for Drew Academy library
Drew Academy schedule for completion at the end of September 2018

CARVER HIGH SCHOOL

July 2018 Updates

The removal of the tile in the cafeteria has been completed and the new tile has been installed. The roof demolition in three roof areas is scheduled to begin in late summer. Carver High School Repair Project is currently 15% complete and the completion is scheduled for late Summer of 2019.

Carver High School tiles has been removed in the cafeteria

Floor has been washed and prep for the new flooring to be put down

EISENHOWER Sr. HIGH SCHOOL FIRE HYDRANT

July 2018 Updates

The trenching and installation of the water line has been completed. The water line is 100% complete. The water meter has also been installed. This project is complete.

Medium Mechanical Repair Project

July 2018 Updates

The cleaning of coils, repairing valves and replacement of fan belts continues. The air handling units are being installed at Aldine 9th Grade, Hill Elementary, Keeble EC/PK/K, Raymond Elementary and Wilson Elementary.

Conley Elementary School

July 2018 Updates
Plumbing in the restrooms are underway and tile has been installed at Conley Elementary

The mechanical repairs are underway with duct work installation. New doors have also been installed in various hallways and entrances. The project is currently 50% complete and final completion is scheduled for late Winter of 2018.

LED LIGHTING AND BUILDING UPGRADE PROJECT AT VARIOUS SCHOOLS

The installation of the LED lights and replacement of ceiling tile and grid continues and is 65% complete. This project is scheduled to be complete by the end of the Summer of 2018.

Stovall Academy

Stehlik Elementary Lighting Installation

Kujawa Elementary School Ceiling tile has been replaced

DREW ACADEMY

July 2018 Updates

The Drew Academy Repairs Project includes replacement roofing, the installation of laminated wall panels in all corridors, office space renovations, ceiling grid and tile replacements, LED lighting upgrade, remodeling of restrooms, and the construction of a new interior storefront glass entry at the library.

The roof replacement is underway and is 60% complete. The new air conditioning units were installed on the roof and mechanical room for the auditorium.
The replacement of the ceiling tile and grid is underway and is 55% complete.

CONLEY ELEMENTARY

JUNE 2018 Updates

The Conley Elementary Repair Project includes restroom upgrades, replacement of doors, upgrading finishes in staff restrooms and break room, mechanical repairs, ceiling grid, tile replacements and replacement of light fixtures to LED light fixtures in the corridors and in the common areas

Work has started on removing old ceiling tiles.

The project is currently 20% complete and final completion is scheduled for late Winter of 2018.
Conley Restroom in progress for upgrade

ALDINE SENIOR HIGH SCHOOL AND MACARTHUR SENIOR HIGH SCHOOL BUILDING AUTOMATION SYSTEMS REPAIR

June 2018 Updates

The Building Automation Systems Project at Aldine Senior High and MacArthur Senior High include the installation and upgrading of mechanical control devices and systems.

The installation of control wiring has begun at both schools. The project is currently 25% complete and the completion is scheduled for late Winter of 2018.

DREW ACADEMY

June 2018 Updates

The Drew Academy repair project includes replacement roofing, the installation of laminated wall panels in all the corridors, office renovations, ceiling grid and tile replacements, LED lighting upgrade, remodeling of restrooms, and the construction of a new interior storefront glass entry at the library.

Before Construction Pictures at Drew Academy
The roof replacement is underway . The 200-hallway is 20% complete.

Demolition of Drew Academy restrooms started

EISENHOWER SR. HIGH SCHOOL

June 2018 Updates

Fire Hydrant

The Eisenhower Senior High School Fire Hydrant Project includes a fire hydrant, water line installation and water meter vault installation.

Materials arrived to Eisenhower Senior High School for the installation of a water line to the fire Hydrant.

The trenching and installation of the water line has begun. The project is scheduled to be complete by end of the Summer of 2018.

LED LIGHTING AND BUILDING REPAIRS PROJECT AT VARIOUS SCHOOLS

June 2018 Updates

The LED Lighting and Building Upgrade Project consists of Stovall EC/PK/K, Black Elementary School, Bussey Elementary, Calvert Elementary, Carroll Elementary, Carter Academy, Eckert Elementary, Hill Elementary, Kujawa Elementary, Oleson Elementary, Parker Elementary, Reece Academy, Reed Elementary, Stehlik Elementary, Wilson Elementary, Aldine Ninth Grade, Eisenhower Ninth Grade, Mac Arthur Ninth Grade, and Nimitz Ninth Grade. The project includes repair and replacement of ceiling tiles and ceiling grid, upgrading of existing light fixtures to LED lighting fixtures in corridors.

The installation of the LED lights and replacement of ceiling tile and grid is underway at 30% complete.

Kujawa Elementary School the after picture with new LED Lights and ceiling tiles.
VCT demo at MacArthur 9th Grade

MEDIUM MECHANICAL REPAIR

June 2018 Updates

The Medium Mechanical Repair Project at Aldine 9th Grade, Hill Elementary, Keeble EC/PK/K, Raymond Elementary and Wilson Elementary consists of repair and replacement of air handling units, cleaning of cooling and heating coils, replacement of exhaust fans, and chilled water valves.

Created By
Thao Huynh
Appreciate

Report Abuse

If you feel that this video content violates the Adobe Terms of Use, you may report this content by filling out this quick form.

To report a copyright violation, please follow the DMCA section in the Terms of Use.