County Highway 6 (Stillwater Boulevard) July 3, 2018 Construction Update

Project Schedule

This Week (July 2)

  • Crews will be removing reclaimed pavement from the south half of CSAH 6.
  • Curb and sidewalk removals will occur the remainder of the week.
  • The contractor will start installing temporary, above ground water services to all homes and businesses this week.

Future Work

  • Water main and water service work will start next week. It is anticipated to last approximately five to six weeks.
  • Traffic will remain in its current configuration (one-way, westbound only) while work continues on the south half of CSAH 6.
Please follow the posted detour route.

Andrew Giesen: Project Manager (651-430-4336)