July CONSTRUCTION updates TAP & CONTINUE SCROLLING DOWN TO VIEW THE ENTIRE COLLECTION.

FOX POINT LUTHERAN CHURCH

READY TO TAKE A TOUR?

Here is our west-facing portion of our building just before you get to the old entrance.

The date in the right hand corner reads 1950.

OLD & NEW REVEALED

Big, beautiful changes are happening here to celebrate the new and honor our beginnings.

Notice the ceiling! Gone is its barrel shape. The current view follows the original shape of the roof joists - as seen here.

NEW ENTRANCE DOORWAY

The big open space at the end, where the stained glass hung above the altar, is our new entrance. But what of the woodwork and stained glass that was there? It's being re-purposed as a nod to the early days of our church.

STAINED GLASS WINDOW

Behind the welcome desk will be a partial wall. On the opposite side of that wall will be a gathering space with seating. The wood frame and original altar glass will be installed there and back-lit.

NEXT STOP

Entering Fellowship Hall from the new entrance (old Chapel)

INSIDE THE ADMIN ADDITION

Here is our large size conference room in the new administration area.

Beyond the metal framing will be a smaller meeting room and office space for our pastors.

A view from one of the new office windows of Fellowship Hall and one of the new lightwells.

WINDOWS & LIGHTWELL

Featured here are new windows for the east side of the basement and another lightwell to admit light to some of the basement rooms.

OUTSIDE VIEW OF THE NEW SANCTUARY ADDITION
SOUTHEAST CORNER OF THE ADMIN area.
BEAUTIFUL DETAILING ADDED TO THE CORNER OF THE NEW SANCTUARY.
PORTE-COCHERE COLUMN BASES ARE NOW ENCASED WITH BRICK
Let US Head back inside the NEW ENTRANCE to view more...
ANOTHER VIEW OF THE ADMIN ADDITION.
LOOK HOW CLEAN PASTOR BILL'S OFFICE IS!
metal stud framinG for brand new restrooms.
MOVING DOWN TO THE BASEMENT. THIS IS THE SMALL GROUP EAST ROOM, WHICH IS UNDERNEATH THE NEW ADMIN section. LOOK AT THE AMOUNT OF NATURAL LIGHT COMING IN from the new lightwell!
OUR FORMER GREEN ROOM IS NOW THE NEW COMMONS AREA. New windows and light well allow for NATURAL LIGHT to beam in.
I SPY A NEW COFFEE BAR! WHERE DO YOU SUPPOSE THIS IS LOCATED?

ANSWER: SMALL GROUP EAST ROOM! (Note to self; remember to visit this location when the building reopens!)

PRESCHOOL ROOM has an awesome new location.
BACK UPSTAIRS TO SEE THE INSIDE VIEW OF THE NEW SANCTUARY ADDITION.

Some building tasks that have been crossed off the list this month!

Crown Carpentry

  1. Week of July 7 – Crown has been busy all around the project working on metal stud framing including finishing the week working on the steel stud framing of the barreled ceiling of the porte-cochere.
  2. Week of July 14 – They increased their crew size this week and have been busy all around the project, but they focused on layout/ framing of the new walls and ceilings in the area of the new main entrance.
  3. Week of July 21 – Continued working all around the project as they are getting close to wrapping up their detail work on the metal stud framing. We’re getting close to starting drywall!
  4. Week of July 28 – Continued work on metal stud walls and bulkheads and started closing up ceilings and walls.

Brand Safway

  1. Delivered and erected temp shoring in the lower-level below the existing concrete floor in the main sanctuary.

Cardinal Fabricating

  1. AGM Erecting has continued to work on wrapping up the last of the “squeeze plate lintels” at the new window and door openings.

Cornerstone Plumbing

  1. Continued roughing in the new water, drain, and vent piping within the new metal stud walls throughout the project.
  2. Worked on the new roof drains and overflow piping on the 2 lower roof sections ahead of the roofers.
  3. Continued to work on new supply, drain, and vent piping throughout. Schedule inspections ahead of drywall that is scheduled to begin

Design Build Fire Protection

  1. July 7 - DBFP continued work in the north side of the project as they’ve installed new sprinkler piping in the areas in and surrounding the new music room in the lower-level as well as continued work in the bell tower and up into the steeple!
  2. July 14 - Continued work throughout this week, but continued to focus on the north side of the project.
  3. July 21 - There is now a sprinkler head within 24” inside of the Cross atop the Church steeple!
  4. July 28 - Continued working on the new sprinkler piping throughout.

I.T. Connect

  1. Worked with the Church to finalize network design elements and create a final design including a list of all hardware components and a plan/ line drawing that can be shared with the construction team.
  2. Finalized the plan of the network design including a list of all hardware components and a plan/ line drawing that can be shared with the construction team at the upcoming walkthrough.
  3. Continued working with Jeff Shoemaker/ Fox Point Lutheran Church to complete the access control, security, and network requirements.

JC Building Systems

  1. JCBS continued working on wood blocking this week, but turned their focus to the exterior. Installed the wood blocking for the roof edge coping and framing required ahead of the roofers return.
  2. Taken delivery of the new decorative columns of the porte-cochere. This was a long lead time order we’re happy to have on site. We are storing these in the Church garage to keep them safe. Assisted with construction cleaning.
  3. Took delivery of our new windows, borrowed lights, and wood doors on Wednesday. Window installation began in the new office addition. Select demo/ wood framing was performed at the new door #117 in fellowship hall.
  4. Completed installing wood blocking in the metal stud walls at the door jambs, windows, millwork locations, and restroom accessories. Completed installation of exterior windows and temp doors. Took delivery of the 2nd load of borrowed lights/ windows.

Pella Windows

  1. Delivered the remaining windows, doors and borrowed lights to the site.

Lyon’s Electric

  1. Worked throughout the project and continued to rough in new devices and cabling in the metal stud walls behind Crown Carpentry. Additionally, work continues on new feeder conduit installation between new panel locations.
  2. Continued roughing in metal conduit and cabling within the metal stud walls. Continued on layout and working on refeeding existing circuits.
  3. Worked on layout and roughing in of the new devises and cabling within the new metal stud walls.

Northern Concrete

  1. Northern set and poured the concrete topping in the sanctuary addition. This topping creates the level surface over the precast plank and is both the final concrete floor of the sanctuary and will later carry the raised stage floor of the chancel.
  2. Poured the remaining concrete toppings on the 1st floor on either side of the sanctuary floor.

Notions Roofing

  1. Early July – Nations visited the site this week to work out our plan for next week’s final new flat roof installation on either side of the sanctuary addition.
  2. Middle July –Worked on the final new flat roof installation on either side of the sanctuary addition. We weren’t able to get the north addition water tight ahead of the large storms, but we’re within a week of making this happen.
  3. Late July – Completed the flat lower roof areas of the sanctuary addition.

Pure Mechanical

  1. Continued work with their larger crew this week and have been busy installing the new ductwork in the lower-level in the area of the new music room and throughout the office addition.
  2. Continued work on fabricating and installing the new ductwork and duct insulation throughout this week. Also worked on roughing in control wiring and boxes and extending the new gas lines to new furnace locations.

Paun Construction

  1. Continued to be the largest presence on site as they are running up the new brick veneer. They have effectively completed the office addition and are currently working on the sanctuary addition. On rain days, they have been working on the new window openings in the lower-level as well as new masonry opening in the south wall of the old chapel.
  2. Paun continued working on the brick veneer this week, though the rain did hamper our progress. Focussed on the lower-level brick around the new windows in the commons as well as the veneer on the sanctuary addition.
  3. Continued with the brick veneer around the rest of the project and on new window openings in lower-level walls as opportunities arise.

Masterfoam

  1. Week of July 7 - Continued work in the upper attic space above the main sanctuary. The humidity can be a real factor for them, but they are careful to assess conditions ahead of every application to ensure a quality product. There were a couple days this week where conditions prevented their work.
  2. Week of July 14 - Wrapped up the last of the areas that can be reached in the sanctuary attic.
  3. Week of July 21 - Wrapped up the sanctuary attic including the underside of the new metal deck above the new addition.
  4. Week of July 28 - Work also began in the area above the lobby and above the old narthex of the Chapel.

A note from the Project Manager...

We are “teed up” to achieve a major milestone! Before the end of the month, we will be substantially weather tight! This triggers a schedule update, which will become our “completion schedule” and will be the road map that takes us through completion.

Stay tuned for more updates!