Arch Systems here we come!

Over the last two weeks, our construction team:

  • Hauled in backfill material for the Contech Arch Systems
  • Began assembling the Arch Systems
  • Installed the silt fence around Lake Bennet
  • TerraMax Engineering provided the design CAD & PDF drawings for the project
  • The City approved the Stormwater Pollution Prevention Plan (SWPPP)
  • Installed all safety signs
  • Established the location for the security cameras
  • Submitted permit for the Maine Street Extension

March 9, 2020

  • Assembly of Arch 6 & 7
  • Dumptruck continue to dump dirt around the lake
  • Continuing moving and rolling dirt

March 10, 2020

  • Completion of Arch 8 and Assembly of Arch 9
Meeting Notes:
  • Columns approx. start between 3/15 to 4/28
  • Arches may halt for bulkhead placement
  • Approx. Sept for both lots and road extension completed

March 11, 2020

  • Completion of Arch 9 and Arch 10
  • Continuing moving and rolling dirt

March 12, 2020

  • Assembly and Completion of Arch 11
  • Assembly of Arch 12
  • Continuing moving and rolling dirt

March 13, 2020

  • Completion of Arch 12
  • Assembly and Completion of Arch 13 (5 remain before bulkhead placement)
  • Continuing moving and rolling dirt