JOHNSON ELEMENTARY SCHOOL ALDINE INDEPENDENT SCHOOL DISTRICT

AISD Johnson Elementary School

Opening 2018-2019 School Year

Construction commenced in April 2017

Johnson Elementary School is located on a new 22 acre site on Homestead Rd. East in Harris County. It includes 150,000 sf building with 52 classrooms, science and computer labs, RTI and Dyslexia facilities, library, art studio, music hall, cafeteria, and gymnasium. The site plan includes separate bus and student drop off areas.

June 2017 Aerial View

June 2017 Updates

The installation of foundation drilled piers is 90% complete. The installation of underground plumbing and electrical work at the pad is 50% complete. Pier caps and grade beams are in process. The first two slab pours out of eight at the building pad are scheduled for mid-June. The detention pond excavation is complete. Site storm piping installation as well as sanitary and water lines have started.

The site has been completely cleared and the building pad preparation is in progress.

July 2017 Aerial View

August 2017 Updates

Construction commenced in April 2017. The first two slab pours out of five at the building pad have been completed with the third scheduled for mid-August. Concrete pier caps and grade beams are in progress. Steel erection is in progress and is 20% complete. The installation of underground plumbing and electrical work at the building pad has been completed. The installation of forms for the north parking and bus drive concrete paving is in progress.

Steel Erection Started
August 2017 Aerial View

SEPTEMBER 2017 UPDATES

Four slab pours out of five at the building pad have been completed with the final pour scheduled for late September. Steel erection is in progress and is 40% complete. Roofing installation is in progress.

Exterior metal wall studs and sheathing board has started installation. The north parking and bus drive concrete paving has been completed and work continues on the west parking.

OCtober 2017 Updates

All slab pours have been completed.

Steel erection is in progress and is 60% complete. Roofing installation is in progress and is 20% complete. Exterior metal wall studs and sheathing board is in progress. The west parking lot has been poured.

October 2017 Aerial View

Front View of Johnson Elementary School

November 2017 Updates

Steel erection and metal decking is in progress and is approximately 75% complete.

Exterior wall installation is in progress. Windows are being installed. Roofing installation is approximately 35% complete. .Slabs at parking areas are 75% complete.

November 2017 Aerial View

December 2017 Updates

Steel erection and metal decking is in progress and is approximately 90% complete. Exterior wall installation is in progress. Windows are being installed. Roofing installation is approximately 80% complete. Interior wall stud installation is in progress.

Drywall started

JAnuary 2017 Updates

Steel erection and metal decking is complete. Exterior wall waterproofing and brick installation is in progress. Windows are being installed. Exterior concrete block installation at the Cafeteria, Library and Gymnasium is in progress. Roofing installation is approximately 90% complete. Interior wall stud and drywall installation is in progress. Parking paving is largely completed.

January 2017 Aerial View

FEBRUARY 2017 updates

Exterior wall waterproofing is complete and brick installation is in progress.

Window installation is 90% complete. Exterior concrete block installation at the Cafeteria, Library and Gymnasium is complete. Roofing is complete. Interior wall stud and drywall installation is in progress. Mechanical, electrical, and plumbing rough-in is 90% complete. Parking paving is complete and sidewalks are in progress.

February 2017 Aerial View

Restroom Area

MArch 2017 updates

Interior drywall and door frame installation is in progress. Ceramic wall tile installation at restrooms is underway. Mechanical, electrical, and plumbing rough-in is complete. Acoustical ceiling grid installation is underway. Pouring of sidewalks is in progress.

Exterior brick installation is 60% complete.

Gymnasium Area

April 2017 updates

April 2017 Aerial View

Exterior brick and stone installation is 95% complete. Interior drywall priming and painting is in progress. Casework installation is underway. Ceramic wall tile installation at restrooms is nearing completion. Acoustical ceiling grid installation is underway. Mechanical chillers have been installed. Pouring of sidewalks is in progress.

MAy 2017 updates

Exterior of the building is complete except for metal fascia and soffit installation. Interior drywall final painting is in progress. Casework installation is in progress. Installation of acoustical ceiling tile is underway. Installation of VCT flooring is is progressing. Avadek exterior canopy installation at main entries is underway. Pouring and forming of site sidewalks is in progress

June 2018 Updates

July 2018 Updates

Interior and exterior of the building are complete. All building systems are operational. Fencing and playgrounds are complete and landscaping installation is nearing completion.

Trees bushes and plants are placed around the entire school.

Playground installation is completed
Cafeteria area is near completion

Serving area

Main Entry is near completion

Furniture has started to move in
Furniture in the flex space area

Graphic designs is near completion throughout cafeteria area.

August 2018 Updates

Johnson Elementary Front Entrance

School Opened August 20, 2018
Created By
Thao Huynh
Appreciate

Report Abuse

If you feel that this video content violates the Adobe Terms of Use, you may report this content by filling out this quick form.

To report a Copyright Violation, please follow Section 17 in the Terms of Use.