AISD Johnson Elementary School
Opening 2018-2019 School Year
Johnson Elementary School is located on a new 22 acre site on Homestead Rd. East in Harris County. It includes 150,000 sf building with 52 classrooms, science and computer labs, RTI and Dyslexia facilities, library, art studio, music hall, cafeteria, and gymnasium. The site plan includes separate bus and student drop off areas.
June 2017 Updates
The installation of foundation drilled piers is 90% complete. The installation of underground plumbing and electrical work at the pad is 50% complete. Pier caps and grade beams are in process. The first two slab pours out of eight at the building pad are scheduled for mid-June. The detention pond excavation is complete. Site storm piping installation as well as sanitary and water lines have started.
The site has been completely cleared and the building pad preparation is in progress.
August 2017 Updates
Construction commenced in April 2017. The first two slab pours out of five at the building pad have been completed with the third scheduled for mid-August. Concrete pier caps and grade beams are in progress. Steel erection is in progress and is 20% complete. The installation of underground plumbing and electrical work at the building pad has been completed. The installation of forms for the north parking and bus drive concrete paving is in progress.
Exterior metal wall studs and sheathing board has started installation. The north parking and bus drive concrete paving has been completed and work continues on the west parking.
OCtober 2017 Updates
All slab pours have been completed.
Steel erection is in progress and is 60% complete. Roofing installation is in progress and is 20% complete. Exterior metal wall studs and sheathing board is in progress. The west parking lot has been poured.
November 2017 Updates
Steel erection and metal decking is in progress and is approximately 75% complete.
Exterior wall installation is in progress. Windows are being installed. Roofing installation is approximately 35% complete. .Slabs at parking areas are 75% complete.
December 2017 Updates
Steel erection and metal decking is in progress and is approximately 90% complete. Exterior wall installation is in progress. Windows are being installed. Roofing installation is approximately 80% complete. Interior wall stud installation is in progress.
JAnuary 2017 Updates
Steel erection and metal decking is complete. Exterior wall waterproofing and brick installation is in progress. Windows are being installed. Exterior concrete block installation at the Cafeteria, Library and Gymnasium is in progress. Roofing installation is approximately 90% complete. Interior wall stud and drywall installation is in progress. Parking paving is largely completed.
FEBRUARY 2017 updates
Exterior wall waterproofing is complete and brick installation is in progress.
Window installation is 90% complete. Exterior concrete block installation at the Cafeteria, Library and Gymnasium is complete. Roofing is complete. Interior wall stud and drywall installation is in progress. Mechanical, electrical, and plumbing rough-in is 90% complete. Parking paving is complete and sidewalks are in progress.
MArch 2017 updates
Interior drywall and door frame installation is in progress. Ceramic wall tile installation at restrooms is underway. Mechanical, electrical, and plumbing rough-in is complete. Acoustical ceiling grid installation is underway. Pouring of sidewalks is in progress.
Exterior brick and stone installation is 95% complete. Interior drywall priming and painting is in progress. Casework installation is underway. Ceramic wall tile installation at restrooms is nearing completion. Acoustical ceiling grid installation is underway. Mechanical chillers have been installed. Pouring of sidewalks is in progress.
MAy 2017 updates
Exterior of the building is complete except for metal fascia and soffit installation. Interior drywall final painting is in progress. Casework installation is in progress. Installation of acoustical ceiling tile is underway. Installation of VCT flooring is is progressing. Avadek exterior canopy installation at main entries is underway. Pouring and forming of site sidewalks is in progress
June 2018 Updates
July 2018 Updates
Interior and exterior of the building are complete. All building systems are operational. Fencing and playgrounds are complete and landscaping installation is nearing completion.
August 2018 Updates
School Opened August 20, 2018