What is happening?
Major building additions, renovations, and approximately 82 acres of site development. 595,000 SF in building work that consists of 250,000 SF classroom addition, 92,000 SF athletics addition, 37,000 SF auditorium addition, and 216,000 SF of existing building renovations.
Schedule
- 3-Story Classroom Addition Completion December 2022
- Fieldhouse Completion December 2022
- Area J (Hammerhead) Completion 8/26/22
- Start Interior Renovations January 2023
- Start Auditorium Addition January 2023
Weekly Updates
Work in Progress
Site Work:
- Installing track surfacing
- Installing turf at the West Fields
- Concessions – installing door frames at the bathrooms & framing bathroom ceilings
3-Story Classroom Addition:
- Interior Finishes:
- Painting – Level 1 Area L & Level 2 Area N
- ACT Grid Install - Area L Level 1 & Area N Level 2
- Tile Install – Area L&M Level 1
- Terrazzo in Coordiors – Area M Level 1
- MEP Rough-In at the penthouses
Fieldhouse:
- MEP Rough-In throuhout
- Installing Track Railing
- Exterior Brick Veneer
- Installing Storefront Frames
- Framing / Sheet rocking / Taping Interior Walls
Locker Rooms:
- Sheetrock / Taping
- Tile Install in toilet rooms
Area J (Hammerhead):
- Painting
- Installing Ceiling Grid
Upcoming Work
Sitework:
- Louricas Turf Install 9/20
- Parking Lot & Road Paving End of August
- Pressbox Install 8/17-8/24
3-Story:
- Curtainwall Area F (Union Area)
- Install Wood Veneer Wall Covering
- PLAM Casework Install
Fieldhouse:
- Slab Pour in Fieldhouse
- Topping pour on overhead track
- Painting Aux Gym
Locker Room:
- Locker Delivery End of October
VIDEOS
Photos
Kraus-Anderson
Jason Peterson, Senior Project Manager | jason.peterson@krausanderson.com
AJ Lillesve, Project Manager | AJ.lillesve@krausanderson.com
Alex Titterud, Project Manager | alex.titterud@krausanderson.com
Cody Darling, Assistant Project Manager | cody.darling@krausanderson.com
Joe Yerbich, Project Superintendent | joe.yerbich@krausanderson.com
Brad Kloos, Project Superintendent | brad.kloos@krausanderson.com
Jarrod Peterson, Assistant Superintendent | jarrod.peterson@krausanderson.com
Taylor Becker, Project Coordinator | taylor.becker@krausanderson.com
Wold Architects
Ben Beery, Associate | bbeery@woldae.com
Maria Kennedy, Architect | mkennedy@woldae.com
Cosette Hannula, Architect | channula@woldae.com