CSAH 19 (Woodbury Drive) & Local Roads Safety Improvement Project July 2, 2020 Construction Update

Project Update

  • In the Hudson Road & Norma Lane intersection, the final layer of asphalt was paved and the traffic signal work was completed. This intersection is now open to traffic.
  • The first two layers of asphalt were paved on Tamarack Road. Median and pedestrian ramp work is currently taking place. Street lights will be installed followed by trail paving and turf restoration work next week into the following week.
  • On Woodbury Drive from I-94 to Commerce Drive, curb and gutter was installed. This area is being graded for paving and the first two layers of asphalt will be paved next week.
  • On Woodbury Drive from Commerce Drive to the south, storm sewer installation was completed and earth work has begun. Curb and gutter are scheduled to be installed next week.

Ramp Closure

Beginning Monday, July 6 at 11PM to Tuesday, July 7 at 7AM the I-94 eastbound exit ramp to CSAH 19 (Woodbury Drive) will be CLOSED. This is a one time overnight closure. Please follow the posted detour route.

Road Closures

Traffic is reduced to one lane in each direction on Woodbury Drive until construction is completed. This extends from Brookview Road to north of I-94. Expect delays and consider alternate routes.
Hudson Road and Tamarack Road are closed at CSAH 19 (Woodbury Drive) in order to complete reconstruction activities. Please follow the posted detour route via Commerce Drive.
Please follow the posted detour route.