Northern Cass Schools Construction Updates

What is Happening

A $2.9 million renovation features a 14,562 SF addition that includes a remodel of the music and commons area

Music Area - addition

Work Completed

  • Footings and foundations
  • Backfill

Work in Progress

  • Masonry and steel work
  • In-wall electrical rough-in

Work Upcoming Next Month

  • Roofing
  • Slab-on-grade concrete
New Choir/Band Room viewed from NW to SE
New Instrument Storage, Office, and Music Rooms viewed from SW to NE

MUSIC AREA - Renovation

Work Completed

  • Demolition
  • Below-grade MEP rough-in

Work in Progress

  • Masonry and steel work

Work Upcoming Next Month

  • Masonry and steel work to be completed
  • Slab-on-grade concrete
  • MEP in-wall and above ceiling rough-in
  • Hollow metal doorframes
New Wall in Music Storage Room/Small Group Classroom
New hallway

Commons Area - addition

Work Completed

  • Concrete foundations
  • Backfill
  • FACS Room masonry infill

Work in Progress

  • Masonry and steel work

Work Upcoming Next Month

  • Masonry and steel work to be completed
  • Slab-on-grade concrete
  • Roofing
Serving lines area viewed from NE to SW
New Commons Area viewed from E to W

Commons area - renovation

Work Completed

  • Demolition
  • Below-grade MEP rough-in

Work in Progress

  • Masonry and steel work
  • Electrical relocations and updates

Work Upcoming Next Month

  • Masonry and steel work to be completed
  • Slab-on-grade concrete
  • MEP in-wall & above ceiling rough-in
  • Hollow metal doorframes
Serving lines area
New freezer area

South Entrance Area - addition

Work Completed

  • Demolition
  • Concrete foundations
  • Backfill

Work in Progress

  • Masonry and steel work
  • Electrical relocations and updates

Work Upcoming Next Month

  • Masonry and steel work to be completed
  • Slab-on-grade concrete
  • Aluminum doors and windows
New South Entrance security vestibule

South Entrance area - renovation

Work Completed

  • Demolition
  • Below-grade MEP rough-in
  • Soffit framing

Work in Progress

  • Masonry and steel work

Work Upcoming Next Month

  • Masonry and steel work to be completed
  • Slab-on-grade concrete
  • MEP in-wall and above ceiling rough-in
  • Flooring
  • Aluminum doors and windows
New South entrance area

Kraus-Anderson

Tucker Norton, Project Manager | tucker.norton@krausanderson.com

Luke Daley, Project Engineer | luke.daley@krausanderson.com

Leif Throngard, Project Superintendent | leif.throngard@krausanderson.com

Zerr Berg Architects

Larry Carcoana, Associate Architect | lcarcoana@zbarch.com