Pipestone Area Schools - New Elementary School Construction Updates

CONSTRUCTION ACTIVITIES PROGRESS THIS MONTH

Building Exterior

Work Started

Work Ongoing

  • Curtain Wall Installation
  • Aluminum Door Installation
  • Storefronts

Work Completed

  • Metal Panel

Work Upcoming Next Month

  • North Parking Lot Grading

Area A

2nd Floor (5th Grade Wing)

Work Started

  • Bathroom Fixtures and Partitions
  • Ceiling Pads
  • Carpet and Vinyl Flooring

Work Ongoing

  • Lighting and Electrical Devices
  • Ceramic Tile
  • Ceiling Grid
  • Diffuser Install

Work Completed

  • Painting
  • Casework

Work Upcoming Next Month

  • Doors and Hardware
  • Wall Coverings
1st Floor (Early Childhood Edu., Kindergarten and Elementary Offices)

Work Started

  • Bathroom Fixtures and Partitions
  • Ceiling Pads

Work Ongoing

  • Ceiling Grid
  • Diffuser Install
  • Lighting and Electrical Devices
  • Ceramic Tile

Work Completed

  • Painting
  • Casework

Work Upcoming Next Month

  • Carpet and Vinyl Flooring
  • Doors and Hardware
  • Wall Coverings

Area B

Gymnasium

Work Started

  • Gym Wood Floor (Pictured)

Work Ongoing

Work Completed

  • Mechanical Equipment Startup

Work Upcoming Next Month

  • Bleachers

Area C

2nd Floor (Art and STEAM Classroom)

Work Started

  • Ceiling Pads
  • Carpet and Vinyl Flooring
  • Doors and Hardware

Work Ongoing

Work Completed

  • Casework
  • Bathroom Fixtures and Partitions
  • Ceramic Tile
  • Overhead HVAC, Plumbing, and Electrical
  • Ceiling Grid
  • Diffuser Install
  • Lighting and Electrical Devices

Work Upcoming Next Month

1st Floor (Special Ed., Commons, and Lunch Room)

Work Started

  • Doors and Hardware
  • Ceiling Pads (Pictured)

Work Ongoing

  • Ceramic Tile
  • Ceiling Grid
  • Diffuser Install
  • Lighting and Electrical Devices

Work Completed

  • Casework
  • Bathroom Fixtures and Partitions
  • Overhead HVAC, Plumbing, and Electrical

Work Upcoming Next Month

  • Carpet and Vinyl Flooring
  • Wall Coverings

Area D

2nd Floor (3rd and 4th Grade Wing)

Work Started

  • Carpet and Vinyl Flooring (Pictured)
  • Doors and Hardware
  • Wall Coverings

Work Ongoing

  • Ceiling Pads

Work Completed

  • Lighting and Electrical Devices
  • Diffuser Install
  • Ceramic Tile

Work Upcoming Next Month

Ceiling Pads
1st Floor (1st and 2nd Grade Wing)

Work Started

  • Carpet and Vinyl Flooring
  • Doors and Hardware
  • Wall Coverings

Work Ongoing

  • Ceiling pads

Work Completed

  • Casework
  • Ceramic Tile
  • Lighting and Electrical Devices
  • Diffuser Install
  • Ceiling Grid
  • Bathroom Fixtures and Partitions

Work Upcoming Next Month

Weight Room Addition

Work Started

  • Overhead Mechanical
  • Framing
  • Drywall
  • Taping and Sanding
  • Electrical Rough-ins

Work Ongoing

Work Completed

  • Underground Electrical
  • Slab on Grade

Work Upcoming Next Month

  • Overhead Electrical
  • Painting
  • Windows

Construction Photos and Videos

Weather

  • Construction Days lost to Weather this Month: 2
  • Total Construction Days lost to Weather: 28

Safety

  • Lost Time Days: 0
  • Days Worked Without Lost Time Accident: 271

Rendering images

Contact

Kraus-Anderson

Shawn Lortscher, Senior Project Manager | shawn.lortscher@krausanderson.com | (507) 208-5692

Tyler Kaczmarek, Project Manager | tyler.kaczmarek@krausanderson.com | (701) 866-5402

Bill Born, Superintendent | bill.born@krausanderson.com | (612) 709-0387

Hillary Hughes, Project Coordinator | hillary.hughes@krausanderson.com | (507) 218-3860

ISG Architects + Engineers

Justin Steffl, Associate Principal, Senior Project Manager | justin.steffl@ISGinc.com | (507) 387-6651