County Highway 6 (Stillwater Boulevard) July 26, 2018 Construction Update

Project Schedule

Last Two Weeks (July 9 - July 20)

  • Work began on the permanent water main on July 11th. It is expected to take five to six weeks to complete.

This Week (July 23)

  • A temporary blacktop patch will be installed at the intersection of 22nd Street and Stillwater Boulevard.
  • Work will continue on the replacement of the water main until mid to late August.

Access

Traffic will remain in its current configuration (one-way, westbound only) while work continues on the south half of Stillwater Boulevard
Please follow the posted detour route.

Andrew Giesen: Project Manager (651-430-4336)