Bulkheads Completed!

Over the last two weeks, the construction team finished the assembly of all the ConTech Arch Systems. They fabricated the rebar for building AB, and started the fabrication of building CJ's rebar. The team continued to install the stone columns for building AB. Lastly, they demucked the area as necessary in preparation for the Arch System.

Continued installing stone columns
Installed security cameras
Completed all bulkheads
Uncovered and installed manholes
Continued work on road extension
Pre-drilling holes on Pad A