County Highway 6 (Stillwater Boulevard) October 29, 2018 Construction Update

Project Schedule

This Week (October 29)

  • On Tuesday, October 30th, crews will be paving a thin lift of pavement in preparation of paving the final lift of blacktop, which is scheduled to occur on Thursday, November 1st. During paving, flaggers will be used to direct traffic.

Next Week (November 5)

  • Crews are scheduled to place mulch and grass seed on the north side of the roadway, clean storm sewer pipes, install permanent traffic control signs, paint pavement markings, and clean-up the site.

Future Work

  • Installation of the concrete sidewalk and restoration of disturbed soils on the south side of the roadway is scheduled for the week of November 12th.