County Highway 6 (Stillwater Boulevard) September 5, 2018 Construction Update

Project Schedule

Last Week (August 27)

  • Concerete crews worked on installing curb and gutter.

This Week (September 3)

  • The roadway will be graded in preparation for paving the blacktop.
  • Crews are scheduled to pave on Friday, but this will be dependent on if the gravel road base dries out due to yesterday’s rain event. Once paving is complete, traffic will be shifted to the south side of the roadway and travel will be restricted to eastbound traffic only.

Next Week (September 10)

  • Crews will begin working on the other half of the roadway once traffic is shifted.
Please follow the posted detour route.

Andrew Giesen: Project Manager (651-430-4336)