Loading

Concrete & Rebar Progress Continues

Progress continues at City Center West Orange! Hard at work, our construction team poured 730 cubic yards of concrete for Building CJ's garage light walls, continued drilling stone columns for the foundation, prepared for hydroseeding along the Blackwood extension, and continued to work on the lake road.

August 17th - Monday

  • Laid out points for driller
  • 20 holes pre-drilled
  • Vibro Stone Column driller getting stuck in the ground
  • Slow penetration because of the hard ground
  • Construction stand down due to lightning (2 hours)

August 18th - Tuesday

  • Poured 730 cubic yards on concrete on light walls CJ (2am - 9am)
  • Continued Vibro Stone Columns for Building CJ
  • Smoothed out concrete and began removing wood edges
  • Driller had major leak at end of yesterday, changed out O-ring, repair not successful, mechanic first thing in the morning
  • Vibro getting stuck in ground (30 min)

August 19th - Wednesday

  • Continued removing wood edges on light walls
  • Dug next foundation holes
  • Laid down dirt for hydroseeding and sod along road extension
  • Cleaned up Building CJ muddy areas with new dirt
  • Continued digging Vibro Stone Columns
  • Drilled next column set
  • Vibro getting stuck
  • Caught up with driller
  • Mechanic fixed issues on rig
  • 42 holes drilled
  • Holes collapsing, started skipping every other hole

August 20th - Thursday

  • Continued digging Vibro Stone Columns
  • Filling in dirt around light walls
  • Built next light wall
  • Built up South wall around Conspan Arches
  • Preparing dirt along Blackwood extension for hydroseeding
  • Drilled 35 holes
  • Driller will be down in the AM for mechanical repair, saved 8 holes to pile in the morning

August 21st - Friday

  • Continued preparing dirt along the Blackwood extension for hydroseeding
  • No Vibro Stone Columns
  • RWH mechanic on site to repair rig
  • Removed bottom pulley of mast to change out bearing and reassemble tension cable
  • Installed new pin for bottom pulley on mast
  • Laid out drilling points
  • Construction stand down due to lightning (1 hour)
  • 22 holes pre-drilled

August 24th - Monday

  • Continued installing rebar containers
  • Continued drilling Vibro Stone Columns
  • Continued building up walls between Contech Arches and piling dirt
  • Construction stand down due to lightning (30 min)
  • Drilled 29 holes
  • Vibro getting stuck in ground (30 min)
  • Stone tube getting clogged, have to extract probe to unclog stone tube (30 min)

August 26th - Wednesday

  • Started to dig out light wall 5
  • Continued drilling Vibro Stone Columns
  • Continued building up walls between Contech Arches and piling dirt
  • Removed dirt wall south of the island in Lake Bennet

August 27th - Thursday

  • Laid in rebar on 3rd lightwall
  • Continued building up walls between Contech Arches and piling dirt
  • Continued drilling Vibro Stone Columns

August 28th - Friday

  • Hydroseeded road extension
  • Continued drilling Vibro Stone Columns
  • Continued building up walls between Contech Arches and piling dirt
Created By
Giovanna Gutierrez
Appreciate