Maple River Schools Construction Updates

Maple River Schools' new $63.3 million campus will feature a two-story, 200,000 SF school with new classrooms, administration offices, three gymnasiums, playgrounds, kitchen, café and 500-seat auditorium. The learning spaces will be organized around an elementary wing that includes early childhood classrooms and a separate middle/high school wing that includes ag science and career and tech classrooms. Outdoor spaces will include new parking lots, retention ponds, walking paths and playfields for outdoor learning programs for all students.

Rendering Video

Monthly updates

Floor Plan

Area A

Work in Progress

  • Steel Stud Framing
  • Overhead Mechanical, Electrical, & Plumbing Rough Ins

Work Completed

  • Slab On Grade
  • Topping Slab
  • Footings & Foundations
  • Precast Erection
  • Grouting precast floor and caulking
  • Roofing

Work Upcoming Next Month

  • Mechanical, Plumbing, & Electrical Wall Rough ins

Area B

Work in Progress

  • CMU walls In the Kitchen

Work Completed

  • Slab on Grade
  • Roofing
  • Footings and Foundations
  • Setting precast
  • Steel joists and decking
  • Topping slab at Storm shelter

Work Upcoming Next Month

  • Overhead Mechanical, Electrical, & Plumbing Rough Ins

Area C

Work in Progress

  • Sheet rocking and taping in practice rooms (pictured)

Work Completed

  • Underground mechanical, plumbing, and electrical rough ins
  • Setting AHU units in mechanical room
  • Footings and Foundations
  • Setting precast
  • Setting bar joists
  • Roofing
  • Catwalk Steel

Upcoming Work

  • Overhead rough In mechanical, plumbing, and electrical in the auditorium

Area D

Work in Progress

  • Overhead mechanical, plumbing, and electrical rough ins

Work Completed

  • CMU walls
  • In wall mechanical, plumbing, and electrical rough ins
  • Exterior Kalwall
  • Footings and Foundations
  • Precast Erection
  • Joist and Decking over Varsity Gym
  • Roofing

Work Upcoming Next Month

  • Painting
  • Ceramic tile in bathrooms
Locker bases being set

Area E

Work in Progress

  • Drywall and taping in the offices
  • Overhead mechanical, plumbing, and electrical wall rough ins

Work Completed

  • Slab on grade
  • Underground mechanical, plumbing, and electrical rough ins
  • Final grading for slab on grade
  • Footings and Foundations
  • Precast Erection
  • Joist and Decking over Middle School Gym
  • Underground mechanical, plumbing, and electrical rough ins
  • Topping slab on second floor

Work Upcoming Next Month

  • Painting
  • Ceiling Grid

Area F

Work in Progress

  • Ceilings being installed on 1st and second floor
  • Ceramic tile in bathrooms

Work Completed

  • Painting
  • Ceramic Tile on second floor
  • Metal panels on the exterior
  • Drywall and taping completed on 1st and 2nd floor
  • In wall mechanical, electrical, and plumbing rough ins
  • Framing interior walls at 1st floor
  • Overhead mechanical, electrical, and plumbing rough ins. at 1st and 2nd floor
  • Installing glass in the exterior windows
  • Installing drywall at 2nd floor

Work Upcoming Next Month

  • Flooring at 2nd floor
Ceiling Grid in Area F

Area G

Work in Progress

  • Ceilings being installed

Work Completed

  • In wall mechanical, electrical, plumbing rough in
  • Overhead mechanical, electrical, plumbing rough in
  • Interior wall framing
  • Footings and Foundations
  • Setting precast
  • CMU walls in the shop
  • Slab on grade
  • Roofing

Upcoming Work Next Month

  • Casework being installed
  • Flooring in rooms

Overall site

Work in Progress

  • Underground utilities
  • Grading out onsite piles

Work Completed

  • First Lift Asphalt In West Parking Lot
  • Water Main
  • Electrical in East Parking Lot
  • East Retention
  • West Retention Pond
  • Main Power brought to the school

Work Upcoming Next Month

  • Site Electrical In East Parking lot
  • Curb and gutter In East Parking Lot
  • First Lift of Asphalt in East Parking Lot
Grading piles on site

Videos and Photos

Weather

  • Construction Days Lost to Weather this Month: 0
  • Total Construction Days Lost to Weather: 29

Safety

  • Lost Time Days: 0
  • Days Worked Without Lost Time Accident: 370

Contact information

Kraus-Anderson

Matt Steffen, Project Manager | 507-513-9910 | matt.steffen@krausanderson.com

Chris Johnson, Project Superintendent | 507-316-7914 | christopher.johnson@krausanderson.com

Shawn Lortscher, Senior Project Manager | 507-208-5692 | shawn.lortscher@krausanderson.com

Katie Herrmann, Project Coordinator | katie.herrmann@krausanderson.com

ISG Architects + Engineers

Charlotte Nienhaus, Architect | Charlotte.Nienhaus@ISGInc.com

Bryan Paulsen, Architect | Bryan.Paulsen@ISGInc.com

Steve Schlaak, Mechanical Engineer | Steve.Schlaak@ISGInc.com

Mike Nelson, Electrical Engineer | Mike.Nelson@ISGInc.com

Nathan Hermer, Civil Engineer | Nathan.Hermer@ISGInc.com

Jacob Sonnek, Structural Engineer | Jacob.Sonnek@ISGInc.com

Bob Mickelson, Senior Project Manager | Bob.Mickelson@ISGInc.com

Laura Drager, Marketing Manager | Laura.Drager@ISGInc.com