Eutichos School Creating a Better FutuRe

Dear Friends, We are gratefully sending you an update about the school extension project. Our contractor, Istvan is doing a marvelous job, advancing fast with the work. Come and see!

November 18, 2016: István, the contractor, and Peter, debating on the budget.

December 20, 2016: Foundation is ready

February 2, 2017: Floor structure on place

February 17, 2017: Floor structure insulated

February 17, 2017: Walls arrive.

February 17, 2017: Starting to erect the walls.

February 18, 2017: Roof structure on place.

February 21, 2017: Roof insulation starts

February 27, 2017: interior walls are covered.

To be continued...