County Highway 6 (Stillwater Boulevard) September 11, 2018 Construction Update

Project Schedule

Last Week (September 3)

  • The roadway was graded in preparation for paving the blacktop.

This Week (September 10)

  • Crews will finish paving the south half of the roadway. Following paving, traffic will be shifted to the south side of the roadway and travel will be restricted to eastbound traffic only.
  • Crews will begin working on the other half of the roadway, beginning with milling and then reclaiming.
  • Curb removals will start towards the end of this week.

Next Week (September 17)

  • Curb placement is scheduled to start next week.
  • Grading for the sidewalk will occur, followed by pouring concrete by the end of next week or beginning of the following week (September 24).
Please follow the posted detour route.

Andrew Giesen: Project Manager (651-430-4336)