Kraus-Anderson (KA) will begin construction on two projects for Jackson County Central Schools. Designed by JLG Architects, the $26 million project includes the new 84,000-square-foot Pleasantview Middle School, which features new classrooms, Career and Tech education learning spaces and science classrooms. The new school also adds a new gymnasium, band and choir areas, kitchen and commons area. Interior renovations to Pleasantview Elementary School, located adjacent to the middle school, include air quality upgrades, as well as improvements meeting Americans with Disabilities Act requirements at all district buildings.
Pleasantview Middle School Addition
Floor Plan
Area b - Classrooms, Music Rooms & Gymnasium
Work in July
Classrooms & Music Rooms:
- Complete Exterior Brick
- Install Drywall
Gym:
- Paint
- Doors & Hardware
- Interior Aluminum Window Frames
- Gym Equipment
Upcoming Work in August
Classrooms & Music Rooms:
- Install Windows
- Tape & Sand
Gym:
- Sound wall Panels
- Doors & Hardware
- Interior Aluminum Windows
- Gym Equipment
- Sound Wall Panels
Area C - Kitchen, Administrative & Common Spaces
Work in July
- Wood Blocking
- Interior Framing (Kitchen)
- Complete Roofing (North Tie In)
- Complete Exterior Brick
- Start MEP & Fire Protection Rough-In
- Slab on Grad
Upcoming Work in August
- Hang Drywall
- Tape & Sand
- Paint
- Complete MEP & Fire Protection Rough-In
- Kitchen Hood
- Freezer/Cooler Install
Site Work
Work in July
- North/East Side of Site:
- Grading
- South Side of Site:
- Grading
Upcoming Work in August
- North/East Side of Site:
- Aggregate Base
- Site Lighting Rough-Ins
- Curb & Gutter
- Concrete Paving
- Playground Equipment & Surfacing
- Basketball Hoops
- Striping
- South Side of Site:
- Aggregate Base
- Site Lighting Rough-Ins
- Monument Sign
- Curb & Gutter
Weather
- Construction Days Lost to Weather This Month: 3
- Total Construction Days Lost to Weather: 58
Safety
- Lost Time Days: 0
Riverside Elementary School Renovation and Addition
Weather
- Construction Days Lost to Weather This Month: 0
- Total Construction Days Lost to Weather: 4
Safety
- Lost Time Days: 0
Kraus-Anderson
Shane Butler, Senior Project Manager | shane.butler@krausanderson.com
Dustin Kempf, Project Manager | dustin.kempf@krausanderson.com
Mindy Cruz, Project Coordinator | mindy.cruz@krausanderson.com
Bre Nava, Assistant Project Manager | bre.nava@krausanderson.com
Matt Lundberg, Project Superintendent (Pleasantview Middle School) | matt.lundberg@krausanderson.com
Matt Harder, Project Superintendent (Riverside Elementary School) | matthew.harder@krausanderson.com
JLG Architects
Catherine Dekkenga, Architect | cdekkenga@jlgarchitects.com