Work Continues Along Lakeside september 28 - october 9, 2020

Work continued with rebar, drainage, and vibro stone columns. Concrete was poured, modifications to brick wall occurred and construction crew dealt with the outcome of rainy season in Florida. Getting closer to completion of this phase of construction.

September 28, 2020

  • No Vibro Stone Columns, holes collapsing on driller
  • Continued installing drainage around lake
  • Continued rebar installment and walls
  • Rain over the weekend caused more runoffs in and around light walls

September 29, 2020

  • Continued installing drainage around lake
  • Continued rebar installment and walls
  • Continued Vibro Stone Columns on Building C-J
  • Prepared for concrete pour September 30, 2020

September 30, 2020

  • Concrete poured at 4 a.m.
  • Continuing Vibro Stone Columns on Building C-J
  • Patched up island and curb on road extension
  • Continued installing drainage around lake

October 1, 2020

  • Continued pulling rock from wall to adjust two bricklayers
  • Continued installing drainage system
  • Continued Vibro Stone Column
  • Removed wood walls from foundation

October 2, 2020

  • Continued Vibro Stone Columns, moved closer to escalator section
  • Laid geogrid underneath two brick layers

October 5, 2020

  • Continued Vibro Stone Columns on Building C-J
  • Added drainage to plans and installed them to current drainage system
  • Dug more rebar areas
  • Dug out mud from rain on western-most rebar location
  • Brought fabricated rebar from Building AB

October 6, 2020

  • Continued installing drainage system
  • Placed rebar where mud was removed
  • Continued Vibro Stone Columns and waited on driller to get ahead
  • Continued digging next rabe location

October 7, 2020

  • Filled and compacted dirt around lakeside manholes
  • Cleaned old wood from rebar containers and laid the supports
  • Telehandler is down, no Vibro Stone Columns

October 8, 2020

  • Continued rebar supports
  • Prepared to finish last manhole on easternmost side of lake
  • Ring Power on site to fix telehandler
  • No Vibro Stone Columns and no pre-drilling

October 9, 2020

  • Placed new rebar boxes on South end of C-J Building
  • Dirt has covered all piping along lake; brought dirt to elevation
  • Still waiting for wall to be fixed before moving forward with island and railing installation
  • Continued pre-drilling and Vibro Stone Columns
  • Helicon should be finished with all stone columns between October 20-22, 2020.