Cottage Grove Ravine Regional Park Lower Landing Facility Project August 21, 2020 Construction Update

Project Update

  • Site preparation and building site earthwork is complete.
  • Building foundation was poured.
  • Underground plumbing and electrical are being installed which will be followed by steal columns and final backfilling in preparation for polish concrete floors and walls to be placed.
  • Building walls are set to start being placed in September.
  • Utility work such as the deep well, septic system, and IT fiber continue to progress.

Construction Contact: Eden Rogers (651-430-4352)