Crystal Police Department Construction Updates

The new 23,800 sq. ft. police building will feature efficient, safe work spaces, including a secure, centralized evidence storage area; secure indoor fleet storage; a dedicated space for K9 officer(s); and an up-to-date detention space and expanded locker room space and capacity. Much of the current police department will be demolished, but some will remain to be repurposed as an additional community meeting room for city hall. Numerous energy efficiencies are included in the building's design.

Floor Plan

Work in Progress

  • Managing SWPPP

Work Upcoming Next Month

Weather

  • Construction Days Lost to Weather This Month:
  • Total Construction Days Lost to Weather:

Safety

  • Lost Time Days: 0

Schedule

The design phase and bidding are expected to be complete by the end of 2020, with construction starting in spring 2021 and occupancy in spring 2022.

Kraus-Anderson

Jason Rentmeester, Senior Project Manager | jason.rentmeester@krausanderson.com

Dan Kjellberg, Project Manager | dan.kjellberg@krausanderson.com

Rachel Struckman, Project Coordinator | rachel.struckman@krausanderson.com

Jesse Fiskewold, Project Superintendent | jesse.fiskewold@krausanderson.com

Wold Architects & Engineers

Melissa Stein, Project Architect | mstein@woldae.com