County Highway 6 (Stillwater Boulevard) July 10, 2018 Construction Update

Project Schedule

Last Week (July 2)

  • Crews removed reclaimed pavement from the south half of CSAH 6.
  • Curb and sidewalk removals took place.

This Week (July 9)

  • The contractor will continue installing temporary, above ground water services to all homes and businesses this week.
  • Water main and water service work will start this week. It is anticipated to last approximately five to six weeks.

Access

Traffic will remain in its current configuration (one-way, westbound only) while work continues on the south half of CSAH 6.
Please follow the posted detour route.

Andrew Giesen: Project Manager (651-430-4336)