Lou Vardeman EC PK/K SCHOOL ALDINE INDEPENDENT SCHOOL DISTRICT

LOU VARDEMAN EC PK/K SCHOOL

Opening 2018-2019 School Year

Construction Commenced February 2017

Aldine ISD Lauder EC/Pre-K/K is part of a new 15.4 acre site along with the new Aldine ISD Lauder Rd Middle School. It includes a 104,322 square-foot main building that contains 2 pre-kindergarten classroom clusters, 3 kindergarten classroom clusters, a special population classroom cluster, library, multi-purpose dining with stage, kitchen, and gym, teacher/staff parking, separate bus drop-off, Amphitheater and playground areas.

Detention pond excavation started
Excavation Continues

April 2017 Updates

The detention pond excavation is approximately 85% complete, while the rough grading for parking areas and drives is approximately 75% complete.

The building pad preparation is finished

Detention Pond

Building Pad Near Completion

May 2017 Updates

The detention pond and the south side Staff Parking Lot are completed, while the rough grading for parking areas and drives have also been completed. The building pad drilled piers are completed and grade beam excavations are ongoing. Sanitary sewer and plumbing lines in the building pad are 50% complete.

May 2017 Aerial View

June 2017 Updates

Construction work continues thru out the month of June.

Flyover of Construction Sites in June 2017

JULY 2017 UPDATES

The building pad slab on grade is 100% complete. Crane has been delivered and steel erection is 80% complete. 80% of the parking lots have been poured and completed. The Overall site paving is 85% complete. 75% of the internal road and drives are completed.

Crane working on steel erection
Steel Erection Continues

Main Entry

Parking lots and drives has been poured

2017 July Aerial View

August 2017 Updates

Steel erection is 100% complete. Steel detailing is ongoing and roof deck installation are ongoing. Ceiling mechanical, electrical and plumbing (MEP) rough-ins, clerestory framing, exterior framing and concrete paving at the Service Yard are in progress. The trenching and installation of the primary duct bank for permanent power just started.

August 23, 2017

August 2017 Aerial View

September 2017 Updates

OCtober 2017 updates

Roof deck installation are ongoing. Window frames, overhead mechanical, electrical, plumbing, exterior masonry walls, and face brick are being installed throughout the entire building. Concrete street paving tie-ins to new Connorvale Road has been completed.

November 2017 Updates

Installation of the following continues throughout the entire building: window frames, interior framing, sheathing and wall insulation, ceiling and wall mechanical, electrical, plumbing, exterior masonry walls and exterior face brick.

November 2017 Aerial View

December 2017 Updates

Installation of the following continues throughout the entire building: window frames, interior framing, sheathing and wall insulation, ceiling and wall mechanical, electrical, plumbing, exterior masonry walls and exterior face brick.

The new Connorvale Road and site entry driveways, and the Amphitheater have been completed.

JAnuary 2018 Updates

January 2018 Aerial View

Installation of the following continues throughout the entire building: front entry storefront, interior framing, sheathing and wall insulation, ceiling and wall mechanical, electrical and plumbing, painting and cabinetry.

FEBRUARY 2018 Updates

February 2018 Aerial View

Installation of the following continues throughout the entire building: windows, interior framing and dry wall, hollow metal frames, sound insulation, quarry floor tile, plumbing fixtures, ceramic wall and floor tile, painting, cabinetry in the classrooms and mechanical roof top units.

MArch 2018 Updates

The following installations and activities are ongoing throughout the building in the front entry tower, Media Center / Library, Pre-K, Kindergarten and Special Population classroom clusters, Administration area and offices, Cafetorium, Kitchen and Gymnasium: interior painting, suspended ceiling, lighting and devices. The following has also been completed throughout the building: flooring, Cafetorium stage, casework, display cases and kitchen equipment. Throughout the site, installation of the following continues: landscaping, fire lane pavers, bollards, cable and post fence, concrete light post foundations and. The following has also been completed throughout the site: flag pole installation, entry tower store front, chain link fence, security and entry gates, overhangs for exterior doorways, bus canopy and concrete sidewalks.

April 2018 Updates

April 2018 Aerial View

The following installations and activities are ongoing throughout the building: interior painting touch ups, flooring finishes, stage floor and curtains, serving lines at the cafetorium and fire marshal inspections have been scheduled.

Throughout the site, installation of the following continues: play area striping, sidewalk pavement cleaning, air pave installation at fire lane, and landscaping and hydro-mulching.

MAY 2018 UPDATES

June 2018 Updates

The school has passed final Fire Marshal inspection.
June 2018 Aerial View

July 2018 Updates

Construction commenced on February 2017. The school has passed Harris County Health inspection. The furniture has been moved in. And final punch list is being completed.
School Opened August 20, 2018