Non-stop Construction for One Year! February 1 - February 12, 2021

February marks one year of non-stop construction on-site! These two weeks were a little less busy with movement, as we prepare for the next construction phase of City Center West Orange Phase 1 buildings. But we still had continual progress on-site! Additional foundation boxes were built for the main Phase 1 building. Concrete was poured into those foundation boxes. Site clean-up continued and dirt was brought to foundations to fill-in sides.

February 1, 2021

Installed rebar in foundation boxes.

A completed foundation box ready for concrete.

February 2, 2021

Site clean-up and prepped for concrete pour the next day.

Ready for concrete!

February 3, 2021

Concrete poured at 7 a.m. A total of 390 cubic yards poured - 39 trucks!

Guiding the concrete chute for even distribution within the foundation box.
Smoothing the concrete on each foundation box.

February 4, 2021

General site clean-up.

Dismantled wood from foundations

February 5, 2021

Site cleanup of all Industrial Concrete equipment. Removed concrete wash bins from site.

Stacked all materials.
Moved rebar off of A-B building site to side of road.

February 9, 2021

Filled and dug around foundations.

Pulled dirt away from foundation top edges using rear loader.
Ran the hand roller machine to flatten out the edge of the dirt, revealing foundation sides along the edge

February 11, 2021

Filled dirt in around foundations with front and rear loader.

Loaded dirt in front loader to take to foundations