Foundation Work Continues

We are already two weeks into the month of September, and our construction team is busy making progress on Building CJ's foundation and the road around Lake Bennet. The team installed rebar, poured concrete, and continued to build the wall around and over the Contech Arches. Despite the crazy rain, our team made great progress!

September 1st - Tuesday

  • Continued to build 4th & 5th lightwall for Building CJ
  • Continued the Vibro Stone Columns for Building CJ
  • Moved dirt mounds on Building CJ to raise dirt elevation for road
  • Continued building wall between north Contech Arches

September 2nd - Wednesday

  • Continued to build the 4th and 5th lightwall for Building CJ
  • Laid new Vibro Stone Column points for Building CJ
  • Continued to build the South wall between Contech Arches
  • Moved dirt mounds on Building AB to Building CJ for the road extension
  • Continued to build the wall between the North Contech Arches

September 3rd - Thursday

  • Continued Vibro Stone Columns for Building CJ
  • Moved dirt from Building AB to Building CJ for road extension
  • Continued to build the wall between and over the Contech Arches
  • Continued digging out the 5th lighwall for Building CJ
  • Another rebar truck arrived
  • Rain last night flooded finished light walls
  • Hydro seed along Blackwood is beginning to grow

September 4th - Friday

  • Continued building block wall above Contech Arches and laid geo grid
  • Continued digging Vibro Stone Columns for Building CJ
  • Continued building rebar walls for Building CJ
  • Moved dirt from Building AB to Building CJ for road extension elevation
  • Installed rebar in lightwall 4 for Building CJ

September 8th - Tuesday

  • Continued installing rebar for Building CJ
  • Cleaned roadways from water and mud
  • Laid out new points for Vibro Stone Column in Building CJ
  • Continued building block wall above Contech Arches and laying geo grid

September 9th - Wednesday

  • Flattened out dirt along the Contech Arch walls
  • Rain caused holes in rebar area causing dirt collapse
  • Continued to build wall around Contech Arches
  • Continued digging Vibro Stone Columns

September 10th - Thursday

  • Continued digging Vibro Stone Columns
  • Rain caused slowdowns with puddles making equipment difficult to move around
  • Continued laying geo grid on the North wall of the Contech Arches
  • Dumped dirt for next layer of geo grid and stone bricks
  • Poured 200 cubic yards of concrete

September 11th - Friday

  • No Vibro Stone Columns because the equipment was down
  • Patched up holes around the Contech Arches with cement
  • Continued to bring in stone to fill cement blocks around Contech Arches